Question: MS PROJECT ASSIGNMENT 3 Audit Project 2 Date: April 29, 2020 Due Date: May 8, 2020 till 23:55. This MS Project Assignment is to be

MS PROJECT ASSIGNMENT 3 Audit Project 2 Date: April 29, 2020 Due Date: May 8, 2020 till 23:55. This MS Project Assignment is to be submitted online. In the table below, job definitions, precedence relations and job duration estimates for an audit scheduling project are given. Saturday and Sunday are not regular working days. Daily working hours are 8:00 to 18:00 with a lunch break during 12:00-13:00. The project will start on February 14, 2020 at 8.00 hrs. Duration Estimates (hours) Resource Predecessors Requirement Optimistic (a) Most likely (m) | Pessimistic (b) 2 2 2 2 1 2 2 2 3 2 1 2 5 4 3 4 5 6 4 4 7 11 3 - 3,4 27 107 3,4 2 4 15 4 9 11 4 - 6 9 14 7 9 1113 5 10 10, 113 10 1 1 1 5 11 1 1 1 1 1 L 5 13,14 5 6 7 4 8 3 12 13 15 When obtaining the expected activity duration round off to the higher integer; i.e., 9.2=10; 9.8=10. Let the direct cost of resource usage be 210 TL/hour per unit of resource. a)Apply step 6 of the resource levelling algorithm for only one cycle through steps 2-5 and report the solution obtained. MS PROJECT ASSIGNMENT 3 Audit Project 2 Date: April 29, 2020 Due Date: May 8, 2020 till 23:55. This MS Project Assignment is to be submitted online. In the table below, job definitions, precedence relations and job duration estimates for an audit scheduling project are given. Saturday and Sunday are not regular working days. Daily working hours are 8:00 to 18:00 with a lunch break during 12:00-13:00. The project will start on February 14, 2020 at 8.00 hrs. Duration Estimates (hours) Resource Predecessors Requirement Optimistic (a) Most likely (m) | Pessimistic (b) 2 2 2 2 1 2 2 2 3 2 1 2 5 4 3 4 5 6 4 4 7 11 3 - 3,4 27 107 3,4 2 4 15 4 9 11 4 - 6 9 14 7 9 1113 5 10 10, 113 10 1 1 1 5 11 1 1 1 1 1 L 5 13,14 5 6 7 4 8 3 12 13 15 When obtaining the expected activity duration round off to the higher integer; i.e., 9.2=10; 9.8=10. Let the direct cost of resource usage be 210 TL/hour per unit of resource. a)Apply step 6 of the resource levelling algorithm for only one cycle through steps 2-5 and report the solution obtained