Question: Multi-Choice Section - Choose the one correct answer from the list provided Question 21 (1 point) saved Projects are not performed in isolation but instead

Multi-Choice Section - Choose the one correct

Multi-Choice Section - Choose the one correct answer from the list provided Question 21 (1 point) saved Projects are not performed in isolation but instead involve or affect individuals, groups, and organizations known as project: Stakeholders Resources Shareholders Team members Question 22 (1 point) Saved A document that demonstrates the sequence of activities where activities are represented as rectangles and dependencies as arrows is a(n): Gantt Chart WBS Flow Chart Network Diagram