Question: MULTIPLE CHOICE ( 1 1 ) You're leading a project with a vague scope. After initial discussions, a key stakeholder keeps adding new requirements. How

MULTIPLE CHOICE
(11) You're leading a project with a vague scope. After initial discussions, a key stakeholder keeps adding new requirements. How should you manage this to avoid scope creep?
a) Accept all requirements to maintain good stakeholder relationships.
b) Politely refuse additional requirements.
c) Initiate a formal change request process for new requirements.
d) Only accept requirements that do not impact the budget.
Answer: -
(12) Your team is unclear about the project's objectives. What document should you refer to for clarification?
a) Project Plan
b) Project Charter
c) Scope Statement
d) Risk Register
Answer: -
(13) A stakeholder compares your project's scope management approach to traditional methods. How do you explain the evolution of scope management practices?
a) Discuss only the latest trends in project management.
b) Highlight the differences without relating them to current practices.
c) Detail the historical context and relate it to modern methodologies.
d) Ignore historical methods as irrelevant.
Answer: -
(14) Youre drafting a Project Charter for a new project. What is the most critical element to include?
a) Detailed project schedule
b) High-level project risks
c) Names of all team members
d) Project purpose and objectives
Answer: -
(15) Your project charter was declined due to lack of clarity. What should be your immediate next step?
a) Start the project without approval.
b) Seek feedback to understand the reasons for rejection.
c) Redraft the charter without feedback.
d) Escalate the issue to higher management.
Answer: -
(16) A key user is not able to articulate their requirements clearly. What technique should you use to gather accurate requirements?
a) Assume their requirements based on similar past projects.
b) Use interviewing techniques to extract detailed information.
c) Wait for them to provide requirements later.
d) Start work based on the available vague information.
Answer: -
(17) You need to prioritize requirements from multiple users. What should be your primary consideration?
a) The urgency as expressed by the users.
b) The alignment of requirements with project objectives.
c) Requirements that are easiest to implement.
d) The seniority of the users providing the requirements.
Answer: -
(18) During scope elicitation, you notice conflicting requirements from stakeholders. What is the best way to address this?
a) Choose the requirement of the most influential stakeholder.
b) Hold a meeting with stakeholders to discuss and resolve conflicts.
c) Ignore the conflicting requirements.
d) Escalate the decision to higher management.
Answer: -
(19) How do you ensure that the high-level scope is aligned with business objectives?
a) Regularly update the scope based on team feedback.
b) Validate the scope against the business case and project charter.
c) Only focus on technical aspects of the scope.
d) Align the scope with the strongest stakeholders vision.
Answer: -
(20) While gathering detailed requirements, you realize that some requirements may lead to significant delays. How should you proceed?
a) Ignore these requirements.
b) Communicate the impact to stakeholders and seek direction.
c) Proceed as planned and deal with delays as they come.
d) Remove the requirements without consulting stakeholders.
Answer: -
(21) A team member suggests an innovative way to capture detailed requirements that might save time. What should be your response?
a) Implement the method immediately without evaluating it.
b) Consider the method and evaluate its potential benefits and risks.
c) Reject the method as it deviates from the plan.
d) Postpone its consideration for future projects.
Answer: -
(22) Youre documenting requirements for an IT project. What is a key factor to consider for successful documentation?
a) Focusing on technical jargon to impress stakeholders.
b) Ensuring clarity and comprehensibility for all stakeholders.
c) Making the document as detailed as possible.
d) Using a standardized template without customization.
Answer: -
(23) During a review, a stakeholder suggests changes to the documented requirements. How should you handle this?
a) Immediately make the changes without reviewing their impact.
b) Analyze the impact of changes on the project and discuss with the team.
c) Reject any changes at this stage.
d) Defer the changes to a later phase of the project.
Answer: -
(24) Your project team is debating the scope of the project. What key document should you refer to for clarification?
a) Project Scope Statement
b) Project Charter
c) Project Management Plan
d) Risk Management Plan
Answer: -
(25) How would you ensure that the project scope aligns with the business needs and objectives?
a) By only considering the technical aspects of the project.
b) Through regular meetings with the project sponsor.
c) By frequently changing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!