Question: MULTIPLE CHOICE ( 1 1 ) You're leading a project with a vague scope. After initial discussions, a key stakeholder keeps adding new requirements. How
MULTIPLE CHOICE
You're leading a project with a vague scope. After initial discussions, a key stakeholder keeps adding new requirements. How should you manage this to avoid scope creep?
a Accept all requirements to maintain good stakeholder relationships.
b Politely refuse additional requirements.
c Initiate a formal change request process for new requirements.
d Only accept requirements that do not impact the budget.
Answer:
Your team is unclear about the project's objectives. What document should you refer to for clarification?
a Project Plan
b Project Charter
c Scope Statement
d Risk Register
Answer:
A stakeholder compares your project's scope management approach to traditional methods. How do you explain the evolution of scope management practices?
a Discuss only the latest trends in project management.
b Highlight the differences without relating them to current practices.
c Detail the historical context and relate it to modern methodologies.
d Ignore historical methods as irrelevant.
Answer:
Youre drafting a Project Charter for a new project. What is the most critical element to include?
a Detailed project schedule
b Highlevel project risks
c Names of all team members
d Project purpose and objectives
Answer:
Your project charter was declined due to lack of clarity. What should be your immediate next step?
a Start the project without approval.
b Seek feedback to understand the reasons for rejection.
c Redraft the charter without feedback.
d Escalate the issue to higher management.
Answer:
A key user is not able to articulate their requirements clearly. What technique should you use to gather accurate requirements?
a Assume their requirements based on similar past projects.
b Use interviewing techniques to extract detailed information.
c Wait for them to provide requirements later.
d Start work based on the available vague information.
Answer:
You need to prioritize requirements from multiple users. What should be your primary consideration?
a The urgency as expressed by the users.
b The alignment of requirements with project objectives.
c Requirements that are easiest to implement.
d The seniority of the users providing the requirements.
Answer:
During scope elicitation, you notice conflicting requirements from stakeholders. What is the best way to address this?
a Choose the requirement of the most influential stakeholder.
b Hold a meeting with stakeholders to discuss and resolve conflicts.
c Ignore the conflicting requirements.
d Escalate the decision to higher management.
Answer:
How do you ensure that the highlevel scope is aligned with business objectives?
a Regularly update the scope based on team feedback.
b Validate the scope against the business case and project charter.
c Only focus on technical aspects of the scope.
d Align the scope with the strongest stakeholders vision.
Answer:
While gathering detailed requirements, you realize that some requirements may lead to significant delays. How should you proceed?
a Ignore these requirements.
b Communicate the impact to stakeholders and seek direction.
c Proceed as planned and deal with delays as they come.
d Remove the requirements without consulting stakeholders.
Answer:
A team member suggests an innovative way to capture detailed requirements that might save time. What should be your response?
a Implement the method immediately without evaluating it
b Consider the method and evaluate its potential benefits and risks.
c Reject the method as it deviates from the plan.
d Postpone its consideration for future projects.
Answer:
Youre documenting requirements for an IT project. What is a key factor to consider for successful documentation?
a Focusing on technical jargon to impress stakeholders.
b Ensuring clarity and comprehensibility for all stakeholders.
c Making the document as detailed as possible.
d Using a standardized template without customization.
Answer:
During a review, a stakeholder suggests changes to the documented requirements. How should you handle this?
a Immediately make the changes without reviewing their impact.
b Analyze the impact of changes on the project and discuss with the team.
c Reject any changes at this stage.
d Defer the changes to a later phase of the project.
Answer:
Your project team is debating the scope of the project. What key document should you refer to for clarification?
a Project Scope Statement
b Project Charter
c Project Management Plan
d Risk Management Plan
Answer:
How would you ensure that the project scope aligns with the business needs and objectives?
a By only considering the technical aspects of the project.
b Through regular meetings with the project sponsor.
c By frequently changing
Step by Step Solution
There are 3 Steps involved in it