Question: multiple choice 1 A point in a network, that shows the activity and the precedence lines is : a. Path. b. Node. c. Event. d.
multiple choice
1 A point in a network, that shows the activity and the precedence lines is :
a. Path.
b. Node.
c. Event.
d. Burst.
2 The budget variance is calculated as:
a. Earned value minus actual cost.
b. Cost minus planned value.
c. Planned value minus actual cost.
d. Earned value minus planned value.
3 One of these costs is considered a direct cost?
a. Rent
b. Health benefits
c. Labor
d. Depreciation on equipment
4 The difference between earned value analysis and Gantt charts is :
a. Cost and schedule.
b. Performance.
c. Cost.
d. Schedule and performance.
5 Contingency budget is:
a. Not usually a part of the activity-based costing process.
b. Money that is spent first to lock-in all contract guarantees.
c. The money that must be received before any project work can begin.
d. Valued at a higher rate than non-contingency money when determining project costs.