Question: Multiple Choice 1 point Unit price contracts are most useful when: The design is complete and unchanging The contractor wants maximum risk The project involves

Multiple Choice 1 point
Unit price contracts are most useful when:
The design is complete and unchanging
The contractor wants maximum risk
The project involves multiple contractors
Quantities of work are uncertain
Multiple Choice 1 point Unit price contracts are