Question: multiple choice 1 The late start time should be calculated using a backward pass through the network. a. True b False 2 Networks would NOT

multiple choice

1 The late start time should be calculated using a backward pass through the network.

a. True

b False

2 Networks would NOT be well used for:

a. Planning a construction project.

b. Planning a software upgrade.

c. Planning a wedding.

d. Planning monthly production.

3 One approach for developing project cost estimates is to:

a. Cost the project based on a work package and task basis.

b. Cost the project based on contingency and task reserves.

c. Cost the project based on total packages.

d. Cost the project based on a module basis.

4 A finish to start lag delay is shown:

a. As a subtracted value in the follower's early finish time.

b. Should be shown on the line joining the two sequential nodes .

c. As an added value in the predecessors early start time.

d. As an addition of time to the predecessor's duration.

5 Which of these estimates should be the most accurate?

a. Comparative

b. Definitive

c. Order of magnitude

d. Parametric

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!