Question: multiple choice 1 The late start time should be calculated using a backward pass through the network. a. True b False 2 Networks would NOT
multiple choice
1 The late start time should be calculated using a backward pass through the network.
a. True
b False
2 Networks would NOT be well used for:
a. Planning a construction project.
b. Planning a software upgrade.
c. Planning a wedding.
d. Planning monthly production.
3 One approach for developing project cost estimates is to:
a. Cost the project based on a work package and task basis.
b. Cost the project based on contingency and task reserves.
c. Cost the project based on total packages.
d. Cost the project based on a module basis.
4 A finish to start lag delay is shown:
a. As a subtracted value in the follower's early finish time.
b. Should be shown on the line joining the two sequential nodes .
c. As an added value in the predecessors early start time.
d. As an addition of time to the predecessor's duration.
5 Which of these estimates should be the most accurate?
a. Comparative
b. Definitive
c. Order of magnitude
d. Parametric
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
