Question: Multiple Choice Question 80 A company's planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the

Multiple Choice Question 80 A company's planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs Fixed Indirect matials $150000 Depreciation $60000 Indirect labor Factory supplies 130000 Taxes 10000 50000 13000 Supervision A flexible budget prepared at the 80000 machine hours level of activity would show total manufacturing overhead costs of $293000. $354400 O$330400. O$234400