Question: Multiple Choice Question 83 A company's planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the

Multiple Choice Question 83 A company's planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs: Variable Indirect materials Indirect labor Factory supplies $170000 200000 25000 Fixed Depreciation Taxes Supervision $50000 10000 40000 A flexible budget prepared at the 90000 machine hours level of activity would show total manufacturing overhead costs of $423000. $395000. O $355500. $455500