Question: Multiple Choice Question In Scrum, a release planning meeting is used to ___. Multiple choice question. negotiate which product backlog items the team will attempt
Multiple Choice Question In Scrum, a release planning meeting is used to ___. Multiple choice question. negotiate which product backlog items the team will attempt identify daily goals for project work establish goals and a general plan for the project