Question: Multiple Choice Question What technique is used when setup times at a workstation are sequence dependent? Multiple choice question. Determine the total time of each
Multiple Choice Question What technique is used when setup times at a workstation are sequence dependent? Multiple choice question. Determine the total time of each job sequence permutation considering the setup time and choose the best (lowest) time. Expand the use of Johnson's rule to as many machines or workcenters in the job flow and proceed as usual. Schedule jobs at the workstation with the shortest setup times first, then the next shortest, and so forth