Question: Multiple Select Question Select all that apply What aspects of project change control are documented within a communication plan at the start of a project?
Multiple Select Question
Select all that apply
What aspects of project change control are documented within a communication plan at the start of a project?
Multiple select question.
Time requirements to implement.
How stakeholders will be notified of changes.
The evaluationdecision making process.