Question: Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected

Multiple Versus Single Overhead Rates, Activity Drivers
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:
Activity Expected Cost Activity Driver Activity Capacity
Setting up equipment $429,550 Number of setups 550
Ordering costs 351,500 Number of orders 18,500
Machine costs 858,900 Machine hours 40,900
Receiving 340,300 Receiving hours 8,300
Deoro produces two models of dishwashers with the following expected prime costs and activity demands:
Model A Model B
Direct materials $559,000 $835,000
Direct labor 468,000454,000
Units completed 16,0007,400
Direct labor hours 5,0002,400
Number of setups 370180
Number of orders 6,90011,600
Machine hours 23,50017,400
Receiving hours 2,0006,300
The company's normal activity is 7,400 direct labor hours.
Required:
1. Determine the unit cost for each model using direct labor hours to apply overhead. Round intermediate calculations and final answers to nearest cent.
Unit Cost
Model A $fill in the blank 1
Model B $fill in the blank 2
2. Determine the unit cost for each model using the four activity drivers. Round your answers to nearest cent.
Unit Cost
Model A $fill in the blank 3
Model B $fill in the blank 4
3. Which method produces the more accurate cost assignment?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!