Question: Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected
Multiple Versus Single Overhead Rates, Activity Drivers
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:
| Activity | Expected Cost | Activity Driver | Activity Capacity |
| Setting up equipment | $464,580 | Number of setups | 580 |
| Ordering costs | 327,600 | Number of orders | 18,200 |
| Machine costs | 836,000 | Machine hours | 41,800 |
| Receiving | 364,900 | Receiving hours | 8,900 |
Deoro produces two models of dishwashers with the following expected prime costs and activity demands:
| Model A | Model B | |
| Direct materials | $571,000 | $844,000 |
| Direct labor | $484,000 | $459,000 |
| Units completed | 15,400 | 8,300 |
| Direct labor hours | 5,700 | 1,500 |
| Number of setups | 400 | 180 |
| Number of orders | 5,900 | 12,300 |
| Machine hours | 23,800 | 18,000 |
| Receiving hours | 2,400 | 6,500 |
The company's normal activity is 7,200 direct labor hours.
Required:
1. Determine the unit cost for each model using direct labor hours to apply overhead. Round intermediate calculations and final answers to nearest cent.
| Unit Cost | |
| Model A | $ |
| Model B | $ |
2. Determine the unit cost for each model using the four activity drivers. Round your answers to nearest cent.
| Unit Cost | |
| Model A | $ |
| Model B | $ |
3. Which method produces the more accurate cost assignment? Direct Labor hours or Four activity drivers
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts