Question: My project has 4 phases initiation, planning, execution and closing and overall budget at closing is $9000 and planned value is $7500, Actual cost is
My project has 4 phases initiation, planning, execution and closing and overall budget at closing is $9000 and planned value is $7500, Actual cost is $6,300 and earned value is $5,600 help me finding schedule variance and cost variance also help me finding CPI and SPI a graph with that will also help me. Kindly help