Question: n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000. Short recognizes revenue over time according to percentage of
n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000. Short recognizes revenue over time according to percentage of completion method. The balance sheet shows the following accounts at the end of 2021: A/R of $40,000, Construction in Progress of $200,000, Less: Billings on Construction Contract of $170,000. The income statement shows Income on the contract of $30,000 at the end of 2021.
What was the total estimated cost of the project at the end 2021?
| a. | 1,300,000 | |
| b. | 400,000 | |
| c. | 1,700,000 | |
| d. | None of the answers is correct | |
| e. | 2,000,000 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
