Question: n what order does lean project management occur? Specify value from the customer s standpoint Answer 1 Question 5 Choose.. . 4 2 3 1

n what order does lean project management occur?
Specify value from the customers standpoint
Answer 1 Question 5Choose...4231
Identify the value stream
Answer 2 Question 5Choose...4231
Create project flow without interruptions
Answer 3 Question 5Choose...4231
Establish pull
Answer 4 Question 5Choose...4231