Question: N2 Suppose that a dam project can be built in 4 years at a cost of $250K per year after which the dam will return

N2

Suppose that a dam project can be built in 4 years at a cost of $250K per year after which the dam will return $50K/year in electricity for 40 years (net of maintenance costs). What is the present discounted value of this project, if the discount rate is 4%/year?