Question: Nadia, John, Saba and Kumar are working together on a project. These are the data for each: Nadia: 60 hours, overhead rate 75%, personal
Nadia, John, Saba and Kumar are working together on a project. These are the data for each: Nadia: 60 hours, overhead rate 75%, personal time 10%, $20/hr John: 80 hours, overhead rate 55%, personal time 12%, $40/hr Saba: 80 hours, overhead rate 75%, personal time 10%, $36/hr Kumar: 40 hours, overhead rate 55%, personal time 12%, $20/hr The total direct labour costs is close to Select one: $14,800 $14,300 $15,100 $14,000