Question: Name: BLDG 2 0 1 3 - Worksheet Time & Materials - February 9 t h , 2 0 2 4 Further to your estimating

Name:
BLDG 2013- Worksheet
Time & Materials - February 9th,2024
Further to your estimating assignment (Assignment #3). The owner comes to you and ask to pave the driveway, after you have it finished bringing it up to grade with Granular A.
He wants 50mm of asphalt placed. What is required? You don't pave, you are not a paving company. You asked a paving company to supply a price to do the work, and they give a price of $50,000.00, but doesn't cover prep. The owner doesn't agree, which CCDC document would you start looking at for an agreement for this extra work between yourself and the owner?
You received some unit rates, etc. from the paving sub. So you decided to do a quick estimate yourself to discuss with the owner.
Paving Crew:
Foreman - $45.45/hour
Operator(s)- $40.00? hour
3 Labour(s)- $35.00/hour
Quality Control Administrator - $40.00hr
Traffic Control supplied by paving company is $125hr
Triaxle trucks -2 are required
Paving equipment - Paver & Roller
Floats -2 are required
34 ton truck, 44, crew cab for crew
34 ton truck for foreman
Asphalt costs $197.34? tonne
It will take 8 hours to prep the driveway and 8 hours to pave the driveway.
What else will be required? Here's where some assumptions are required. How would you move forward with this, after you have noted your assumptions (you don't own any equipment)? Prepare and estimate using PH-CC-796, so you can discuss further with the owner, then possible you can switch the extra work over to a lump sum agreement?
Name: BLDG 2 0 1 3 - Worksheet Time & Materials -

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!