Name: Progress and Performance Exercises Date: 1. In month 9 the following project information is available:...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Name: Progress and Performance Exercises Date: 1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? 3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of pe- riod 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8? A 002 < N 202 2 LEGEND ES ID EF SL LS DUR LF SL NON 2 B 8 00000 8 D 0 2 6 8 8 4 12 202 12 2 C 2 4 5 729 729 Project baseline (PV) (in $) E 10 2 3 12 202 505 F 15 3 15 Task DUR ES LF SL (PV) Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 A 2 0 2 0 400 200 200 B 6 2 8 0 2400 200 600 200 600 200 600 C 5 2 9 2 1500 200 400 500 100 300 D 48 12 0 1600 400 400 400 400 E 3 7 12 2 900 300 400 200 F 3 12 15 0 600 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV total 200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 6800 7000 7100 7400 End of Period 4 Task Actual % Complete EV AC PV CV SV A B Finished 300 400 50% 1000 800 33% 500 600 0% 0 E 0% Cumulative Totals Finished End of Period 8 Task A Actual % Complete Finished EV AC PV CV SV 300 400 B 2200 2400 C 1500 1500 D 25% 300 0 E 300 F 0% 0 Cumulative Totals Finished [T 33% End of document Name: Progress and Performance Exercises Date: 1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? 3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of pe- riod 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8? A 002 < N 202 2 LEGEND ES ID EF SL LS DUR LF SL NON 2 B 8 00000 8 D 0 2 6 8 8 4 12 202 12 2 C 2 4 5 729 729 Project baseline (PV) (in $) E 10 2 3 12 202 505 F 15 3 15 Task DUR ES LF SL (PV) Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 A 2 0 2 0 400 200 200 B 6 2 8 0 2400 200 600 200 600 200 600 C 5 2 9 2 1500 200 400 500 100 300 D 48 12 0 1600 400 400 400 400 E 3 7 12 2 900 300 400 200 F 3 12 15 0 600 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV total 200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 6800 7000 7100 7400 End of Period 4 Task Actual % Complete EV AC PV CV SV A B Finished 300 400 50% 1000 800 33% 500 600 0% 0 E 0% Cumulative Totals Finished End of Period 8 Task A Actual % Complete Finished EV AC PV CV SV 300 400 B 2200 2400 C 1500 1500 D 25% 300 0 E 300 F 0% 0 Cumulative Totals Finished [T 33% End of document
Expert Answer:
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date:
Students also viewed these general management questions
-
A firm makes three types of furniture: beds, chairs and tables. The manufacturing times required to make them, the profit and capacity available at each work centre are given below; To make one unit...
-
Natalie and her parents, Janet and Brian, are anxious to examine and analyze the updated financial statements. Natalie has obtained a copy of the financial statements of a major competitor, a public...
-
The following cost information is available for a single product manufactured and sold by Dreamer Corp.: Variable costs: Direct materials $ 10 Fixed costs (in total): (Per unit) Direct labor 12 Fixed...
-
Repeat the calculations of Example 9.5, but for a total solution normality of 0.5. Data From Example 9.5:- For the Cu 2+ /Na + exchange with a strong-acid resin, show how the fraction CuR2 in the...
-
Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): An employee can produce an average of 10 units per month. Each worker on the payroll costs...
-
3. Design NAND-NAND implementation for following functions: a) F1(x, y, z) = (x + y + z)(x' + y' + z') b) F2(x, y) = xy + x'y
-
Two identical particles, each having charge #q, are fixed in space and separated by a distance d. A third point charge -Q is free to move and lies initially at rest on the perpendicular bisector of...
-
4. After graduation you decide to buy your first car. You decide you want to get a Kia because it has a 10 year/100,000 mile warranty. You buy a 2019 Kia Sorrento EX for $35,000 and finance the...
-
In the 21st century, the study of Ecclesiology has now taken center stage. In general, the success and proliferation of alternative church arrangements through the use of technology, namely...
-
The following statements have errors. What are they? class Person { }; private: string name; string address; A constructor with two parameters public: void Person (string n, string a) { } name = n;...
-
Working in teams of female and male members, develop a list of behaviors that could be classified as quid pro quo harassment or hostile environment. Explore the possibility that some sexual harassing...
-
A new engineer is evaluating whether to use a larger-diameter pipe for a water line. It will cost $350,000 more initially, but it will reduce pump- ing costs. The optimistic, most likely, and pes-...
-
1. What is a make file and what is it used for in software development? 2. Describe in your own words what each line of the below make file does. tempconv: tempconv.o g++ -o tempconv tempconv.o...
-
A 200-kg crate is to be supported by the rope-and-pulley arrangement shown. Determine the magnitude and direction of the force P that must be exerted on the free end of the rope to maintain...
-
Some people argue that the internal control requirements of the Sarbanes-Oxley Act (SOX) put U.S. companies at a competitive disadvantage to companies outside the United States. Discuss the...
-
Why does the priority system described in this chapter require that it be open and published? Does the process encourage bottom-up initiation of projects? Does it discourage some projects? Why?
-
NSDC has a contract to produce eight satellites to support a worldwide telephone system (for Alaska Telecom, Inc.) that allows individuals to use a single, portable telephone in any location on earth...
-
Given the time-phased work packages and network, complete the baseline budget form for theproject. Soccer Toy Project & test Legend ESID | EF SL Description LS | DURI LF Soccer Toy Project Cost by...
-
Calculate the ignition delay period (in deg ca) in a diesel engine using Eqns (16.15a) and (16.15b) using the conditions at the beginning of fuel injection that exist after compression in the engine...
-
This question is based on Fig. 16.9. An engine operating on an Otto cycle has a maximum peak pressure of \(60 \mathrm{bar}\). If the pressure and temperature at the beginning of the cycle are 1.0 bar...
-
Compare the air-standard cycle thermal efficiencies of an Otto cycle obtained by calculating the state points around the cycle with the value obtained from Eqn (3.16) for an 'engine' operating with a...
Study smarter with the SolutionInn App