Question: NEC 4 Engineering and Construction Contract main Option C and secondary Options X 6 , X 7 , X 1 1 , X 1 4

NEC4 Engineering and Construction Contract main Option C and secondary Options X6, X7, X11, X14, X16 and X17.
QUESTION 41
Which TWO of the following options include amounts that may be paid by the Contractor when assessing the amount due?
Select TWO options
Amounts under secondary Option X16.
One quarter of the Price for Work Done to Date if the Contractor has not submitted a programme showing the information which the contract requires.
A Defect included in the Defects Certificate that shows low performance compared to the performance level stated in the Contract Data.
Amounts under secondary Option X6.
Delay damages.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!