Question: NEC 4 Engineering and Construction Contract main Option C and secondary Options X 6 , X 7 , X 1 1 , X 1 4
NEC Engineering and Construction Contract main Option C and secondary Options X X X X X and X
QUESTION
Which TWO of the following options include amounts that may be paid by the Contractor when assessing the amount due?
Select TWO options
Amounts under secondary Option X
One quarter of the Price for Work Done to Date if the Contractor has not submitted a programme showing the information which the contract requires.
A Defect included in the Defects Certificate that shows low performance compared to the performance level stated in the Contract Data.
Amounts under secondary Option X
Delay damages.