Question: NEC 4 Option C with X 5 & X 7 It is five weeks after the Contract Date and the Project Manager has received the
NEC Option C with X & X
It is five weeks after the Contract Date and the Project Manager has received the Contractor's first application for payment which was submitted before the assessment date. The Contractor has assessed the Price for Work Done to Date as However, the Contractor has not yet submitted a programme. What amount for the Price for Work Done to Date should the Project Manager include in its assessment of the amount due?
Select ONE option
plus the Fee
less the Disallowed Cost