Question: NEC 4 Option C with X 5 & X 7 It is five weeks after the Contract Date and the Project Manager has received the

NEC 4 Option C with X5 & X7
It is five weeks after the Contract Date and the Project Manager has received the Contractor's first application for payment which was submitted before the assessment date. The Contractor has assessed the Price for Work Done to Date as 100,000. However, the Contractor has not yet submitted a programme. What amount for the Price for Work Done to Date should the Project Manager include in its assessment of the amount due?
Select ONE option
75,000
25,000
75,000 plus the Fee
100,000
100,000 less the Disallowed Cost