Question: Need answer ASAP For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities. NEEDED IN PDM Activity Days

Need answer ASAP

For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities.

NEEDED IN PDM

Activity

Days

Precedents

a

3

-

b

15

A

c

5

A

d

60

A

e

6

D

f

40

B

g

10

c, e

h

7

F

i

6

G

j

12

h, i

i. By using network schedule technique, draw a Network Diagram of above enlisted activities.

ii. Find Critical Path , earliest start, earliest finish , latest start and latest finish from Network Diagram.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!