Question: Need answer ASAP For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities. NEEDED IN PDM Activity Days
Need answer ASAP
For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities.
NEEDED IN PDM
| Activity | Days | Precedents |
| a | 3 | - |
| b | 15 | A |
| c | 5 | A |
| d | 60 | A |
| e | 6 | D |
| f | 40 | B |
| g | 10 | c, e |
| h | 7 | F |
| i | 6 | G |
| j | 12 | h, i |
i. By using network schedule technique, draw a Network Diagram of above enlisted activities.
ii. Find Critical Path , earliest start, earliest finish , latest start and latest finish from Network Diagram.