Question: NEED ANSWER ASAP The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time Using the data in
NEED ANSWER ASAP
The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time
Using the data in the table, what is the minimum possible time required for completing the project?
ACTIVITY IMMEDIATE TIME
PREDECESSOR
A - 4
B - 3
C A 2
D B 7
E C, D 4
F B 5
Using the data in the table, what is the minimum possible time required for completing the project?