Question: need answer fast MV-Send 1. The project manager who has estimated the time for a project. Using the data below to: a. Draw the AON

need answer fast
MV-Send 1. The project manager who has estimated the time for a project. Using the data below to: a. Draw the AON and appropriate legend (3 marks) b. Calculate Forward Pass, Backwards Pass, Slack Time (FP: 5 marks, BP: 5 marks, SL Time: 5 Marks c. Determine the Critical Path or paths and the length of the project (2 marks) Activity A B Please note that if a calculation mistake is made then all subsequent steps will receive a score of O. Please do the work carefully. Description Immediate Units of Time Predecessors Activity 1 2. Activity 2 A 3 Activity 3 A 10 Activity 4 A 13 Activity 5 A 18 Activity 6 CD 15 Activity 7 BF Activity 8 EG 9 M D G 10 H 5 CA 80093Step by Step Solution