Question: Need capacity bills PMP week 1 2 3 end panels 14 39 50 shelves 20 25 50 9. Birchmark Industries makes two items for the
Need capacity bills

PMP
| week | 1 | 2 | 3 |
| end panels | 14 | 39 | 50 |
| shelves | 20 | 25 | 50 |
9. Birchmark Industries makes two items for the furniture industry: end panels and shelves. Routing and standard time data for the two items are shown below. Item Lot size Operation Machine center Setup time (hr.) Run time per unit (hr.) End panels 60 1 of 3 2 of 3 3 of 3 1 of 3 2 of 3 3 of 3 Saw Planer Router Saw Planer Router 0.7 hours 0.25 0.0 0.1 0.25 0.5 0.1 hours 0.15 0.075 0.06 0.03 0.06 Shelves 100