Question: NEED DONE IN EXCEL. step by step SSR Corp, a wheel rim supplier to a major motorcycle manufacturer uses a Kanban system to control material
SSR Corp, a wheel rim supplier to a major motorcycle manufacturer uses a Kanban system to control material flows to their customer. The wheel rims are sent in groups of 12. The stamping process can generate approximately 200 wheel rims per hour. It takes one hour for the wheel rim to be moved from the SSR's facility to the customer processes. Due to variations in processing times due to the varying types of the wheel rims for different motorcycle specifications, it has been decided to keep 25 percent of the needed inventory as safety stock. How many Kanban card sets are needed