Question: need HELP ASAP ! Suppose a project is in its performing stage. At the end of week 14, the project team meets to evaluate the
need HELP ASAP !
Suppose a project is in its performing stage. At the end of week 14, the project team meets to evaluate the progress of the project. The project total budgeted cost is 325.783 dollars. The project completion time is 36 weeks. The project cumulative earned value is 163,935 dollars and the project cumulative budgeted cost is 121,498 dollars. The project has consumed 130,912 dollars. If the project continue to perform at the current cost performance index, the estimated project cost at completion is ___dollars. Use at least 4 decimals