Question: need help asap. will thumbs up! Midco's executives have decided that, considering the business environment, the current expected duration of the project is not competitive.



Midco's executives have decided that, considering the business environment, the current expected duration of the project is not competitive. They want to ensure that the probability of completing the project in 8 months ( 240 days) is at least 80%. By how many days should the expected project duration be shortened? Assume crashing actions do not impact the variance of the activity durations. The longest path is: ABCD This path takes forty-two days to complete. As a result, 42 days is the anticipated project duration. 2b. Tables of ES, EF, LS, LF, and Slack Times: 2c. The critical path is ABCD, and the project is projected to take 42 days to complete