Question: need help on this question! FOJECT MANAGEMENT P1. A project consists of 10 ectivities, lettored A through J, as shown in tho eccompanying estimate in

need help on this question!
need help on this question! FOJECT MANAGEMENT P1.
FOJECT MANAGEMENT P1. A project consists of 10 ectivities, lettored A through J, as shown in tho eccompanying estimate in weeks is whown in the following of able. estimate in wecks is shown in the following table. b. Esculurer the patas tarouga the network. b. What is the duration of each of the paths? c. What is the critical path? d. What is the second-most critical path? c. What is the slack time for each activity? f. Calculate the BS, EF, LS and LF times for each activity