Question: Need help please! For the following project, calculate the expected time according to PERT. Maintain one decimal place. Act. ID Description Predecessor Optm. (a) Most
Need help please!

For the following project, calculate the expected time according to PERT. Maintain one decimal place. Act. ID Description Predecessor Optm. (a) Most Pess. (b) Expected Likely (m) time Design None 6 8 16 Package Design Product - 16 24 26 W N Build Package 6 7 10 4 Secure patent 2 11 20 28 Build product 2 8 12 20 Paint 3,4,5 4 7 10 Test market 6 15 16 19 Complete the table with the expected time for each activity
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts