Question: need help Question 1 - You decided to open a production facility. The following figure shows the process flow diagram. You hired 5 employees, and

need help Question 1 - You decided to open a

need help

Question 1 - You decided to open a production facility. The following figure shows the process flow diagram. You hired 5 employees, and each employee performs one task. A HEHEHE 5 min 8 min 2 min 6 min 2 min A - How many units can you produce in 8 hours? (2) | B - Where do you have work-in-process inventory? (show it on the above flow chart) (2) C-What is the labor productivity? (2) D - How many people do you hire at least to make Task A the new bottleneck? (2)