Question: need help with 3, and 4 show work please Question 3 (1 point) Saved Project N has the following cash flows: YEAR 0 1 2
Question 3 (1 point) Saved Project N has the following cash flows: YEAR 0 1 2 CASHFLOW _(5000) 6000 8000 The IRR (Internal Rate of Return) for Project B is: 100% Zero % 10% 50% Question 4 (1 point) Saved Project WIN has the following cash flows: -1200 C1 C2 C3 C4 +285 400 600 700 The IRR (Internal rate of return) of the project is: (Approximately) IRO