Question: Need help with A, dont need B You run a construction firm. You have just won a contract to build a government office complex. Building
You run a construction firm. You have just won a contract to build a government office complex. Building it will require an irvestment of $10.3 million today and $4.8. milion in one year. The govemiment will pay you $21.4 milion in one year upon the building's completion. Suppose the inferest rate is 10.7%. a. What is the NPV of this opportunity? b. How can your firm tum this NPV into cash today? a. What is the NPV of this oppoctunity? The NPV of the proposal is \& million. (Round to two decimal places.)