Question: Need help with this question An end item has the product structure diagram given in the figure below: a. Write the product structure diagram as

Need help with this question
An end item has the product structure diagram given in the figure below: a. Write the product structure diagram as an indented bill-of-materials (BOM) list. b. Suppose that the MPS for the end item is Week 30 31 35 32 300 33 220 34 200 MPS 165 180 240 If the production is scheduled on a lot-for-lot (L4L) basis, find the planned order release for component F. c. Using the data in part (b), find the planned order release for component I. End item C(1) A(3) 1 week B(2) 2 weeks 2 weeks D(1) 3 weeks E(1) 2 weeks F(1) 1 week G(2) 1 week Figure 1: Product Structure Diagram H(3) 4 weeks 1 weekStep by Step Solution