Question: Need help with this question Question 2 You supervise the project for building a new bike production facility. The following table shows the activities be

Need help with this question Question 2 YouNeed help with this question

Question 2 You supervise the project for building a new bike production facility. The following table shows the activities be done. Activity A B D E F G H Immediate Predecessor None None A A, B B C, D D E Activity time 3 5 4 3 9 4 4 6 A- Draw the network diagram with early and late start time and early and late finish time of each task, and identify the critical path? (8)