Question: Need Number 1,2 please D Question 1 1 pts A company just paid $10 million for a feasibility study. If the company goes ahead with
D Question 1 1 pts A company just paid $10 million for a feasibility study. If the company goes ahead with the project, it must immediately spend another $114,119,427 now, and then spend $20 million in one year. In two years it will receive $80 million, and in three years it will receive $90 million. If the cost of capital for the project is 11 percent, what is the project's NPV? Question 2 1 pts A company just paid $10 million for a feasibility study. If the company goes ahead with the project, it must immediately spend another $100 million now, and then spend $20 million in one year. In two years it will receive $80 million, and in three years it will receive $90 million. If the cost of capital for the project is 11 percent, what is the project's IRR? % terms to 2 decimal places and without the % sign