Question: Need some assistance with this question, please show work if applicable. Thank you! Two critical path activities are candidates for crashing on a project. Activity

Need some assistance with this question, please show work if applicable. Thank you!

Need some assistance with this question, please

Two critical path activities are candidates for crashing on a project. Activity details are in the table below. To cut one day from the project's completion time, activity should be crashed first, adding to project cost Activity B Normal Time Normal Cost 8 days $6,000 10 days $4,500 Crash Time 6 days 9 days Crash Cost $6.800 $5,000 Select one: a. A and B, 5900 0 b. A and B $1,300 0 C. A $800 0 d. B, S500 e. A, $400