Question: NEED THE ANSWER BEFORE 12:45! PLEASE AND THANKS b) What is the probability that activity Falone will take between 44 and 46 days? The following

NEED THE ANSWER BEFORE 12:45! PLEASE AND THANKS

NEED THE ANSWER BEFORE 12:45! PLEASE AND THANKS

b) What is the probability that activity Falone will take between 44 and 46 days? The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Activity Optimistic Time (days) Most Likely Time (days) Pessimistic Expected Variance Time Time of (days) (days) Activity 1-3 A of 19 Start D End 10 16 28 B 20 28 42 E F 18 30 42 15 15 15 E 1 2 3 F 42 45 48 a) What is the probability that this project will be delayed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!