Question: Need the bottom two, got the gross requirements from multiplying the table top requirements by 4 for the legs and leg brackets, there is no

Need the bottom two, got the gross requirements from multiplying the table top requirements by 4 for the legs and leg brackets, there is no given scheduled receipts. gave prior weeks info.
You should notice that the Gross Requirements (demand) information for the finished tables has changed a bit (in the Week 72 Blank tab) since the week 71 planning activity shown on the Week 71 Solved tab. For the week 75 Gross Requirements we are now using the actual customer orders for week 75, whereas before we were simply substituting a forecast (average) value. You will also see that we now have demand information week 78, where we are using the forecast (average) value of 30.
You should also notice that the current number on hand (at the start of week 72) is not always equal to the number that we were planning to have (e.g. the Projected On Hand value at the end of week 71) when we planned this out back in week 71. This is because things don't always go according to plan.
As you fill out the tables, assume you would not expedite an order only for the purpose of replenishing safety stock. You may have periods in which there is a Net Requirement, but you can't back up by the normal lead time and place a new order within the current planning horizon. In these cases, leave Planned Receipts equal to zero (or blank) and just let the Net Requirement carry into the next period.
Also, don't have Planned Receipts in periods that have no Gross Requirement. You may have a period in which there is a Net Requirement (carried over from the previous period) in a period that has no Gross Requirement. In this case, leave Planned Receipts equal to zero (or blank) and just let the Net Requirement carry into the next period.
You should fill out these tables by entering the correct values into the cells of the MRP tables.
Blank MRP Tables (MRP Lecture) On Hand: Safety Stock: 15 10 72 73 74 75 76 77 27 28 35 30 30 30 (-) (-) Planning weeks 71-77: Item # 123456EA (Early American Table) Lot Size: 75 Lead Time: 2 weeks Week 71 Gross 33 Requirements Scheduled 75 Receipts Projected 15 57 On Hand Net Requirements Planned Receipts Planned 75 Releases 30 77 42 12 57 27 8 28 75 75 75 On Hand: Safety Stock 5 15 On Hand: Safety Stock 40 40 On Hand: Safety Stock: 652 200 72 73 74 75 76 77 73 74 76 77 71 73 74 75 76 77 72 0 75 0 0 72 450 0 0 75 0 0 0 0 (-) ) 0 300 0 0 (-) ) 420 416 400 400 400 (+) Planning weeks 71-77 Item # 111223EA (Early American Table Top Lot Size: LFL (Lot-for-Lot) Lead Time: 1 weeks Week 71 Gross 75 Requirements Scheduled 80 Receipts Projected On Hand 5 10 Net Requirements 5 Planned X Receipts Planned Releases Planning weeks 71-77: Item #5555567 Leg Bracket) Lot Size: 2000 Lead Time: 1 weeks Week Gross Requirements Scheduled Receipts Projected 652 on Hand Net Requirements Planned (+) Planning weeks 71-77: Item # 111334EA (Early American Table Les Lot Size: LFL Lead Time: 2 weeks Week 71 Gross 300 Requirements Scheduled 310 Receipts Projected 40 50 On Hand Net Requirements Planned Receipts Planned Releases 10 10 15 15 15 15 i 50 50 40 40 40 40 232 1782 1366 966 566 2166 2166 5 5 80 290 418 34 80 (+) 290 (+) 2000 2000 Receipts 80 290 2000 Planned Releases 2000 *Total requirements from ALL PRODUCTS THAT USE THIS BRACKET On Hand Safety Stock: 7,000 5,000 72 73 74 75 76 77 17,300 15,200 14,300 14,300 Planning weeks 71-77: Item # 999999 (Oak Stock) Lot Size: 10,000 lin ft. (Multiples) Lead Time: 1 weeks Week 71 Gross Requirements 14,400 Scheduled Receipts 20,000 Projected 7000 On Hand 12,600 Net Requirements Planned Receipts 5,300 10,100 5,800 11,500 11,500 11,500 9,700 14,900 9,200 13,500 10,000 20,000 10,000 20,000 Planned Releases 10,000 20,000 10,000 20,000 *Total requirements from ALL PRODUCTS THAT USE THIS OAK STOCK 55 On Hand: Safety Stock: 10 73 74 75 76 77 78 28 35 25 30 EA123456 Table, Early American 30 30 (-) Demand comes from customers 75 0 0 0 0 0 (+) 0 5555567 (4) Leg Bracket 40 15 60 EA111223 (1) Table Top, Early American 30 EA 111334 (4) Table Leg, Early American 0 Demand comes from production of 0 45 0 15 0 0 the parent 999999 (24 lin. ft.) Oak Stock 999999 (4 lin. ft.) Oak Stock 0 75 0 0 75 0 (+) item 0 75 0 0 0 0 Item # 123456EA (Early American Table) 5 Lot Size: 75 5 Lead Time: 2 weeks - Week 72 Gross Requirements 27 Scheduled 0 Receipts Projected 0 On Hand 55 28 Net 1 Requirements 0 Planned 0 2 Receipts Planned 3 Releases 75 4 5 6 Planning weeks 72-78: 7 Item #111223EA (Early American Table Top) 8 Lot Size: LFL (Lot-for-Lot) 9 Lead Time: 1 weeks 0 Week 72 Gross 1 Requirements 108 Scheduled 2 Receipts Projected 10 3 On Hand Net 4 Requirements Planned 5 Receipts Planned 6 Releases 7 8 10 46 On Hand: Safety Stock: On Hand: Safety Stock: 15 40 Planning weeks 72-78: Item # 111334EA (Early American Table Leg) Lot Size: LFL (Lot-for-Lot) Lead Time: 2 weeks Week 72 73 Gross 108 112 Requirements 73 74 75 76 77 78 74 75 76 77 78 112 140 100 120 120 120 (-) 140 100 120 120 120 (-) (+) +) (+) Scheduled Receipts Projected On Hand 46 Net Requirements Planned Receipts Planned Releases Blank MRP Tables (MRP Lecture) On Hand: Safety Stock: 15 10 72 73 74 75 76 77 27 28 35 30 30 30 (-) (-) Planning weeks 71-77: Item # 123456EA (Early American Table) Lot Size: 75 Lead Time: 2 weeks Week 71 Gross 33 Requirements Scheduled 75 Receipts Projected 15 57 On Hand Net Requirements Planned Receipts Planned 75 Releases 30 77 42 12 57 27 8 28 75 75 75 On Hand: Safety Stock 5 15 On Hand: Safety Stock 40 40 On Hand: Safety Stock: 652 200 72 73 74 75 76 77 73 74 76 77 71 73 74 75 76 77 72 0 75 0 0 72 450 0 0 75 0 0 0 0 (-) ) 0 300 0 0 (-) ) 420 416 400 400 400 (+) Planning weeks 71-77 Item # 111223EA (Early American Table Top Lot Size: LFL (Lot-for-Lot) Lead Time: 1 weeks Week 71 Gross 75 Requirements Scheduled 80 Receipts Projected On Hand 5 10 Net Requirements 5 Planned X Receipts Planned Releases Planning weeks 71-77: Item #5555567 Leg Bracket) Lot Size: 2000 Lead Time: 1 weeks Week Gross Requirements Scheduled Receipts Projected 652 on Hand Net Requirements Planned (+) Planning weeks 71-77: Item # 111334EA (Early American Table Les Lot Size: LFL Lead Time: 2 weeks Week 71 Gross 300 Requirements Scheduled 310 Receipts Projected 40 50 On Hand Net Requirements Planned Receipts Planned Releases 10 10 15 15 15 15 i 50 50 40 40 40 40 232 1782 1366 966 566 2166 2166 5 5 80 290 418 34 80 (+) 290 (+) 2000 2000 Receipts 80 290 2000 Planned Releases 2000 *Total requirements from ALL PRODUCTS THAT USE THIS BRACKET On Hand Safety Stock: 7,000 5,000 72 73 74 75 76 77 17,300 15,200 14,300 14,300 Planning weeks 71-77: Item # 999999 (Oak Stock) Lot Size: 10,000 lin ft. (Multiples) Lead Time: 1 weeks Week 71 Gross Requirements 14,400 Scheduled Receipts 20,000 Projected 7000 On Hand 12,600 Net Requirements Planned Receipts 5,300 10,100 5,800 11,500 11,500 11,500 9,700 14,900 9,200 13,500 10,000 20,000 10,000 20,000 Planned Releases 10,000 20,000 10,000 20,000 *Total requirements from ALL PRODUCTS THAT USE THIS OAK STOCK 55 On Hand: Safety Stock: 10 73 74 75 76 77 78 28 35 25 30 EA123456 Table, Early American 30 30 (-) Demand comes from customers 75 0 0 0 0 0 (+) 0 5555567 (4) Leg Bracket 40 15 60 EA111223 (1) Table Top, Early American 30 EA 111334 (4) Table Leg, Early American 0 Demand comes from production of 0 45 0 15 0 0 the parent 999999 (24 lin. ft.) Oak Stock 999999 (4 lin. ft.) Oak Stock 0 75 0 0 75 0 (+) item 0 75 0 0 0 0 Item # 123456EA (Early American Table) 5 Lot Size: 75 5 Lead Time: 2 weeks - Week 72 Gross Requirements 27 Scheduled 0 Receipts Projected 0 On Hand 55 28 Net 1 Requirements 0 Planned 0 2 Receipts Planned 3 Releases 75 4 5 6 Planning weeks 72-78: 7 Item #111223EA (Early American Table Top) 8 Lot Size: LFL (Lot-for-Lot) 9 Lead Time: 1 weeks 0 Week 72 Gross 1 Requirements 108 Scheduled 2 Receipts Projected 10 3 On Hand Net 4 Requirements Planned 5 Receipts Planned 6 Releases 7 8 10 46 On Hand: Safety Stock: On Hand: Safety Stock: 15 40 Planning weeks 72-78: Item # 111334EA (Early American Table Leg) Lot Size: LFL (Lot-for-Lot) Lead Time: 2 weeks Week 72 73 Gross 108 112 Requirements 73 74 75 76 77 78 74 75 76 77 78 112 140 100 120 120 120 (-) 140 100 120 120 120 (-) (+) +) (+) Scheduled Receipts Projected On Hand 46 Net Requirements Planned Receipts Planned ReleasesStep by Step Solution
There are 3 Steps involved in it