Question: Need to create WBS You have been allocated a small project team from the council services to do the site preparation , installation of pathways
Need to create WBS
You have been allocated a small project team from the council services to do the site preparation, installation of pathways, installation of soft-fall base and other facilities, and landscaping. A separate company, Fun Kids Play Equipment has been contracted to supply and install the playground equipment. The quote for the supply and installation of the playground equipment has been accepted and totals $140,000.
Your project team comprises you as Project Manager, a landscape gardener, a concreter and a plumber, and you are all able to help and do general duties. You have access to the councils building, gardening and earth works equipment. Assume that you, the members of the project team, and any contractors can all work 5 days a week.
The following List of Most Important Work will assist with your scope management and other project planning. Please note, this is NOT a Work Breakdown Structure (WBS). You should use the below information to create your own Work Breakdown Structure (WBS) and list of activities.
| 1. | Clear site of waste material |
| 2 | Prepare site (earth works) |
| 3 | Lay concrete pathways |
| 4 | Lay soft-fall base |
| 5 | Install playground equipment |
| 6 | Plumbing for water fountain |
| 7 | Install water fountain |
| 8 | Install rubbish bin |
| 9 | Lay grass around the perimeter |
| 10 | Plant of trees and shrubs |
| 11 | Clear site of building rubbish |