Question: needing help with the cost drivers and activity 1. If $30,000 of Setup is used as an activity cost pool, which of the following would
1. If $30,000 of Setup is used as an activity cost pool, which of the following would be used as a cost driver? a. Square feet b. Number of setups c. Design modifications d. Number of employees hired 2. If $200,000 of Assembly is used as an activity cost pool, which of the following would be used as a cost driver? a. Direct labor hours b. Square feet c. Design modifications d. Number of inspections 3. If $40,000 of Inspection is used as an activity cost pool, which of the following would be used as a cost driver? a. Engineering hours b. Tons recycled c. Number of orders d. Number of inspections 4. If $10.000 of Maintenance is used as an activity cost pool, which of the following would be used as a cost driver? a. Engineering hours b. Design modifications c. Square feet d. Number of orders