Question: Net Present Value ( NPV ) In this assignment, you are required to prepare a PowerPoint presentation reviewing 3 projects. You will calculate the NPV

Net Present Value (NPV)
In this assignment, you are required to prepare a PowerPoint presentation reviewing 3 projects. You will calculate the NPV, IRR, and payback period for each project. Utilizing the capital budgeting calculations, you will need to select the best investment for the company. These calculations will be based on the following scenario:
AIU Industries has 3 potential projects to consider, all with an initial cost of $1,250,000. The company prefers to reject any project with a 4-year cut-off period for recapturing initial cash outflow. Given the cost of capital rates and the future cash flow for each project, determine which project the company should accept.
\table[[Cash Flow,Project A,Project,Project U],[Year 1,250,000,450,000,250,000],
[Year 2,250,000,450,000,400,000],
[Year 3,250,000,450,000,600,000],
[Year 4,250,000,450,000,800,000],
[Year 5,400,000,400,000,200,000],
[Year 6,400,000,400,000,800,000],
[Year 7,400,000,400,000,600,000],
[Year 8,400,000,400,000,200,000],
[Cost of Capital,4%,6%,8%]
Must be 15 slides ( power point ).
Provide the calucations NPV , IRR and payback for each project. Show work.
 Net Present Value (NPV) In this assignment, you are required to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!