Question: Net Present ValueUnequal Lives Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an

Net Present ValueUnequal Lives

Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $750,000. The net cash flows estimated for the two proposals are as follows:

The estimated residual value of the processing mill at the end of Year 4 is $280,000.

Present Value of $1 at Compound Interest
Year6%10%12%15%20%
10.9430.9090.8930.8700.833
20.8900.8260.7970.7560.694
30.8400.7510.7120.6580.579
40.7920.6830.6360.5720.482
50.7470.6210.5670.4970.402
60.7050.5640.5070.4320.335
70.6650.5130.4520.3760.279
80.6270.4670.4040.3270.233
90.5920.4240.3610.2840.194
100.5580.3860.3220.2470.162

Determine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present value table appearing above. If required, round to the nearest dollar.

Processing MillElectric Shovel
Present value of net cash flow total$$
Less amount to be invested$$
Net present value$$

Which project should be favored? SelectElectric ShovelProcessing MillItem 7

Net Present ValueUnequal LivesBunker Hill Mining Company has two competing proposals: a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!