Question: Network Analysis Given this WBS , draw out a network diagram and use the two - pass and enumera methods to answer the following questions.
Network Analysis
Given this WBS draw out a network diagram and use the twopass and enumera methods to answer the following questions.
tableActivityPredecessor,Durationa daysbcadaeafb cgdhd eifjg h
Question point
Saved
Consider the network above. What is the critical path for this project?
b
acfi