Question: Network Analysis Given this WBS , draw out a network diagram and use the two - pass and enumera methods to answer the following questions.

Network Analysis
Given this WBS, draw out a network diagram and use the two-pass and enumera methods to answer the following questions.
\table[[Activity,Predecessor,Duration],[a,-,5 days],[b,-,4],[c,a,3],[d,a,4],[e,a,6],[f,b, c,4],[g,d,5],[h,d, e,6],[i,f,6],[j,g, h,4]]
Question 6(1 point)
Saved
Consider the network above. What is the critical path for this project?
a-d-g-j
b-f-i
a-c-f-i
a-e-h-j