Question: NETWORK ANALYSIS I ( PROBLEM ) Critical Path Method ( CPM ) The project of a minor redesign of a product and its associated packaging

NETWORK ANALYSIS I (PROBLEM)
Critical Path Method (CPM)
The project of a minor redesign of a product and its associated packaging consists of following activities:
\table[[Activity,,Completion],[number,time (weeks),],[1,Redesign product,6],[2,Redesign packaging,2],[3,Order and receive components for redesigned product,3],[4,Order and receive material for redesigned packaging,2],[5,Assemble products,4],[6,Make up packaging,1],[7,Package redesigned product,1],[8,Test market redesigned product,6],[9,Revise redesigned product,3],[10,Revise redesigned packaging,1],[11,Present results to the Board,1]]
\table[[\table[[Activity],[number]],\table[[activity],[number]]],[must be finished before,can start],[2,4],[3,5],[4,6],[5,6,7],[7,8],[8,9],[8,10],[9,10,11]]
(i) Draw the project network diagram.
(ii) Find the critical path and the minimum time required to complete the project.
(iii) Also compute the slack time available with each activity.
 NETWORK ANALYSIS I (PROBLEM) Critical Path Method (CPM) The project of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!