Question: NETWORK ANALYSIS PROBLEM 3 DURATION RESOURCE. ANALYSE THE NETWORK, SHOW THE CRITICAL PATH AND COMPLETE THE TABLE BELOW. DRAW A BAR CHART SHOWING ALL ACTIVITIES

NETWORK ANALYSIS PROBLEM 3
DURATION
RESOURCE.
ANALYSE THE NETWORK, SHOW THE CRITICAL PATH AND COMPLETE THE TABLE BELOW.
DRAW A BAR CHART SHOWING ALL ACTIVITIES AT EARLIEST START DATES.
FROM THE BAR CHART SHOW THE RESOURCE REQUIREMENTS IN THE FORM OF A HISTOGRAM.
112
SOLUTION OF NETWORK ANALYSIS PROBLEM 3
\table[[\table[[ACTIV.],[EVENT],[NOS.]],DURATION,EARLIEST,LATEST,FLOAT],[START,FINISH,START,FINISH,TOTAL,FREE,INDEPENDENT],[1-2,6,,,,,,,],[1-3,5,,,,,,,],[1-5,2,,,,,,,],[2-7,4,,,,,,,],[3-4,6,,,,,,,],[4-7,0,,,,,,,],[4-10,3,,,,,,,],[5-6,3,,,,,,,],[6-8,7,,,,,,,],[6-9,2,,,,,,,],[7-9,4,,,,,,,],[7-10,2,,,,,,,],[8-9,2,,,,,,,],[9-10,5,,,,,,,]]
NETWORK ANALYSIS PROBLEM 3 DURATION RESOURCE.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!