Question: NETWORK ANALYSIS PROBLEM 3 DURATION RESOURCE. ANALYSE THE NETWORK, SHOW THE CRITICAL PATH AND COMPLETE THE TABLE BELOW. DRAW A BAR CHART SHOWING ALL ACTIVITIES
NETWORK ANALYSIS PROBLEM
DURATION
RESOURCE.
ANALYSE THE NETWORK, SHOW THE CRITICAL PATH AND COMPLETE THE TABLE BELOW.
DRAW A BAR CHART SHOWING ALL ACTIVITIES AT EARLIEST START DATES.
FROM THE BAR CHART SHOW THE RESOURCE REQUIREMENTS IN THE FORM OF A HISTOGRAM.
SOLUTION OF NETWORK ANALYSIS PROBLEM
tabletableACTIVEVENTNOSDURATION,EARLIEST,LATEST,FLOATSTARTFINISH,START,FINISH,TOTAL,FREE,INDEPENDENT
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
