Question: Network and Resource Loading Given the network diagram below (Fig 1), compute the early, late, and slack times. Assume ONE of each resource is available.
- Network and Resource Loading Given the network diagram below (Fig 1), compute the early, late, and slack times. Assume ONE of each resource is available. Fill in the blanks in the network nodes.
Q1. What is the project duration?
Q2. What is the projects critical path (illustrate it on your diagram)

Q2. Using any approach you wish (e.g. trial and error) develop a resource loading chart (Fig 2) for resources Painter (P) and Trimmer (T).
Q3. After resource loading, has the project duration changed? Explain.
NETWORK DIAGRAM Resources: Painter); Trimmer) (ONE of each resource is available) B P D T 3 4 0 F P P 3 3 E P T 1 2 ES ID EF SL source LS Dur LF Resource Loading Schedule for Tasks A-F Painter AAACBBBB FFF Trimmer E E DDD Day 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 .....etc 5 6 7