Question: Network Diagrams & PERT Question: We are remodeling the da Vinci Lounge in the Spencer Engineering Building. A. Identify the critical path B. Identify the

Network Diagrams & PERT Question:

We are remodeling the da Vinci Lounge in the Spencer Engineering Building.

A. Identify the critical path B. Identify the slack for each element C. Identify the most and least sensitive element D. Identify the predicted project duration (TE) E. Z is the number of standard deviations from the mean found in the statistical table below, and defined by the relationship: Z = (Ts - TE) / SQRT(te2 ) where only critical path te are included in the summation. If the companys scheduled time to complete the work (Ts) is 70 days, then what is the likelihood that we finish the remodeling project on time? Express your probability response as a percentage rounded to the nearest integer.

Network Diagrams & PERT Question: We are

Network Diagrams & PERT Question: We are

Variance Likely Worst Time est. (days) M B TE =(A+(4M)+B)/6 St. Dev Ote =(B-A)/6 Ote^2 4 6 Activity Preceding Best activity A a. Rough in 3 walls b. Redo Tim 4 Hortons C. run HVAC 12 a 6 11 15 30 bc 12 15 20 d. rough in electrical e. complete flooring f. windows 7 12 a 22 e 2 17 19 de 13 17 19 f 5 10 15 g. install fire alarm h. deliver llounge chairs . exposed ceiling reviews j. murals g 11 13 20 g,h 12 12 13 16 8 12 22 k. sound system z Value Probability z Value Probability -2 0.02 2 0.98 -1.5 0.07 1.5 0.93 -1 0.16 1 0.84 -0.7 0.24 0.7 0.76 -0.5 0.31 0.5 0.69 -0.3 0.38 0.3 0.62 -0.1 0.46 0.1 0.54

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!