Question: Network nodes can be created using MS Excel, or compatible software. You have signed a contract to build a garage for the Simpsons. You will

Network nodes can be created using MS Excel, or compatible software.
You have signed a contract to build a garage for the Simpsons. You will receive a
$500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days.
1. Draw a project network given the following information. (10 points)
2. Complete the forward and backward pass compute activity slack (5 points)
3. Identify the critical path. (2.5 points)
4. Create a Gantt Chart for the project (10 points)
5. Do you expect to receive a bonus or a penalty on this project? (2.5 points)
Garage
ID Description Predecessor Time
A Prepare Site None 2
B Pour Foundation A 3
C Erect Frame B 4
D Roof C 4
E Windows C 1
F Doors C 1
G Electrical C 3
H Rough-in Frame D,E,F,G 2
I Door Opener F,G 1
J
K Paint
Cleanup H,I
J 2
1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!